Final Inspections & Handover

Certificate of Occupancy, punch list, and keys in the homeowner's hand.

Typical duration: 1–3 weeks
3 steps
0/17 complete
13–10 days

Municipal Final Inspections & Certificate of Occupancy

All trade finals, energy verification, and the CO that makes the house legally habitable.

Builder / Super
Inspections

Prerequisites & handoff

  • All trade finals scheduled
  • Site clean and safe
  • Address numbers posted

Critical measurements & tolerances

  • Blower-door and duct-leakage results at or under code targets, documented
  • Egress windows: min 5.7 sq ft net clear opening (5.0 at grade floor), 24" clear height, 20" clear width, sill max 44" AFF
  • Guardrails at any walking surface more than 30" above grade; 4" sphere rule
  • Smoke / CO alarms interconnected and functioning
  • Handrail graspability and continuity along the full flight
  • Address numbers min 4" high, contrasting, visible from the street

Permits & inspection milestones

  • Building final inspection
  • Plumbing / mechanical / electrical finals
  • Energy compliance certificate posted at the panel
  • Final grading and erosion control release
  • Certificate of Occupancy issued

Field tips & tricks

  • Run your own mock final with the code checklist two days before the inspector. Fix the five items you find quietly.
  • Have the permit card, approved plans, truss drawings, energy certificate and test reports in one binder on the counter.
  • Take the SWPPP down only after final grading release — an early removal can hold your CO.

Field checklist

0 / 6 complete
  • All trade finals passed
  • Energy certificate posted
  • Egress and guard dimensions verified
  • Alarms tested
  • Grading release obtained
  • Certificate of Occupancy in hand
21–2 weeks

QA Punch List & Final Clean

Builder punch, trade returns, verification punch, then detail clean.

Builder / Super

Prerequisites & handoff

  • CO issued or pending
  • All trades notified of punch window

Critical measurements & tolerances

  • Doors and drawers operate and align; reveals consistent
  • Paint inspected under raking light and normal room lighting from 6' distance
  • Every window and door opens, locks, and weather-strips
  • All fixtures, outlets, and switches operated once and logged
  • Grout and caulk lines continuous at all wet-area changes of plane

Permits & inspection milestones

  • None — internal quality gate

Field tips & tricks

  • Punch room by room, clockwise, ceiling to floor. Blue tape everything and photograph each tag into the punch log.
  • Hold trade retainage until punch items are verified, not just reported complete.
  • Do the final clean after punch, then lock the house. One trade walking through undoes a $900 clean.

Field checklist

0 / 5 complete
  • Builder punch complete
  • Trades returned and verified
  • Second verification punch clean
  • Final detail clean done
  • House locked and keyed
31–2 days

Homeowner Orientation & Keys Handover

Walk the house, train the owner on systems, deliver documents, hand over keys.

Builder / Super

Prerequisites & handoff

  • CO issued
  • Punch closed
  • Warranty package assembled

Critical measurements & tolerances

  • Demonstrate: main water shutoff, gas shutoff, panel and breakers, thermostat, GFCI reset, irrigation timer
  • Filter sizes and replacement intervals written down
  • Warranty terms: typically 1 year workmanship, 2 years systems, 10 years structural

Permits & inspection milestones

  • Certificate of Occupancy delivered to homeowner
  • Utility accounts transferred

Field tips & tricks

  • Record the orientation walk on video and send it to the homeowner. It eliminates half of the year-one calls.
  • Deliver a binder and a digital folder: CO, permits, manuals, warranties, paint colors with sheens, and every test report.
  • Schedule the 30-day and 11-month warranty visits at the handover while everyone is happy.

Reference documents

View in library →

Field checklist

0 / 6 complete
  • Systems orientation completed
  • Documents and warranties delivered
  • Paint and finish schedule provided
  • Utilities transferred
  • Keys, remotes, and codes handed over
  • Warranty visits scheduled