Jobsite tracker

Create a jobsite for each active project. Each keeps its own checklist progress on this device.

Overall completion · 0/1530%

Current phase: 1. Pre-Construction & Permitting

Zoning & Lot Due DiligenceBuilder / Super · Survey & Engineering

  • Title / easements reviewed
  • Setback envelope drawn on plat
  • Flood zone determination pulled
  • Utility availability confirmed in writing
  • HOA submittal package sent

Geotechnical Report & Boundary SurveySurvey & Engineering

  • Borings complete
  • Geotech report received and forwarded to engineer
  • Boundary + topo survey stamped
  • Corner pins flagged and protected

Construction Documents & EngineeringBuilder / Super · Survey & Engineering

  • Architectural set complete
  • Structural stamped
  • Energy compliance done
  • Trades reviewed plans
  • Plan set printed for field

Permit Submittal, Review & IssuanceBuilder / Super · Inspections

  • Permit issued and card posted
  • Trade permits pulled
  • SWPPP installed and inspected
  • Temp power and temp water set
  • Portable toilet and dumpster on site

Clearing, Erosion Control & Building StakeoutEarthwork · Survey & Engineering

  • 811 locates marked
  • Silt fence and inlet protection in
  • Rock construction entrance built
  • Topsoil stockpiled
  • Offset stakes and benchmark set

Excavation, Pad Build & CompactionEarthwork

  • Cut / fill to subgrade
  • Lifts compacted and tested
  • Density report filed
  • Pad drains away from house

Underground Plumbing & Utility SleevesPlumbing · Electrical · Earthwork

  • DWV installed to slope
  • Test held and inspected
  • Water service and sleeves placed
  • Penetrations photographed and dimensioned

Footings, Forms & Rebar InspectionConcrete

  • Forms set to line and elevation
  • Diagonals verified square
  • Steel chaired, lapped, and tied
  • Rebar inspection passed

Vapor Barrier, Slab Pour & WaterproofingConcrete

  • Vapor barrier sealed
  • Pre-pour inspection passed
  • Slab poured and finished flat
  • Cure protected 7 days
  • Waterproofing and drain installed
  • Backfill compacted in lifts

Sill Plates, Wall Framing & LayoutFraming

  • Sill sealer and PT plates set
  • Walls framed, plumb, and straight
  • Headers per plan
  • Rough openings verified against door / window schedule
  • Blocking and backing installed and photographed

Shear Walls, Straps & Hold-downsFraming · Inspections

  • Sheathing nailing verified
  • Hold-downs installed and torqued
  • Straps fully nailed
  • Shear inspection passed

Floor System, Roof Trusses & SheathingFraming · Roofing

  • Floor system set, glued, screwed
  • Trusses set and braced per drawings
  • Roof sheathed and clipped
  • Truss drawings on site

Roof Dry-in, Windows & Exterior DoorsRoofing · Framing

  • Roof dried in
  • WRB installed shingle-lapped
  • Windows set plumb, level, flashed
  • Exterior doors set and pan-flashed
  • Kickouts installed

Plumbing Rough-inPlumbing

  • DWV and vents complete
  • Water lines run and manifolded
  • Tub / shower pans set and protected
  • Nail plates installed
  • Test held, inspection passed

HVAC Ductwork & Equipment RoughHVAC

  • Manual J / D / S on file
  • Trunks and branches installed and supported
  • Boots sealed with mastic
  • Return paths for all rooms
  • Line sets and flues installed
  • Rough inspection passed

Electrical Rough-in & Home RunsElectrical

  • Panel set and grounded
  • Boxes set to depth and height
  • Home runs pulled and labeled
  • AFCI / GFCI circuits mapped
  • Smoke / CO locations verified
  • Rough inspection passed

Low Voltage, Security & Pre-wireLow Voltage

  • Data / coax pulled and labeled
  • Camera and doorbell runs in
  • Speaker wire and backboxes set
  • Head-end location powered
  • Spare conduits installed

Pre-Drywall Multi-Trade Walk & Framing InspectionBuilder / Super · Inspections · Framing

  • Fire blocking / draft stopping complete
  • All trade rough inspections passed
  • Framing inspection passed
  • Wall bays photographed
  • Homeowner pre-drywall walk done

Air Sealing, Insulation & Blower-Door PrepInsulation

  • Top plates and rim joists sealed
  • Penetrations fire-caulked
  • Baffles installed
  • Insulation to spec, Grade I
  • Pre-drywall blower door run
  • Insulation inspection passed

Drywall Hang, Tape, Texture & PrimeDrywall · Painting

  • Board hung and screwed to pattern
  • Fire-rated assemblies correct
  • Taped and textured to spec level
  • Primed
  • Light-raked and touched up

Interior Doors, Trim & StairsFinish Carpentry

  • Doors hung, reveals even, latching
  • Casing and base installed
  • Stair rise / run verified
  • Handrails and guards to height
  • Caulked and puttied for paint

Cabinets, Countertops & TileFinish Carpentry · Tile & Flooring

  • Cabinets set, level, fastened to blocking
  • Appliance openings verified
  • Tops templated and installed
  • Shower pan flood tested
  • Tile set, lippage checked
  • Flooring moisture tested and installed

Siding, Stucco or Masonry VeneerExterior Skin

  • Lath / WRB inspected
  • Cladding installed to spec
  • Weeps and air space clear
  • Clearances to grade verified
  • Penetrations flashed and sealed

Flatwork, Grading, Gutters & DrainageFlatwork & Grading · Concrete

  • Sub-base compacted
  • Flatwork poured and jointed
  • Final grade sloped away
  • Gutters and extensions installed
  • Drainage verified with a hose test

Plumbing Fixtures & Water Heater Start-upPlumbing

  • Fixtures set and sealed
  • Water heater installed and started
  • PRV / expansion tank verified
  • Appliance connections made
  • Leak check documented

Electrical Trim, Devices & Panel LabelingElectrical

  • Devices and plates installed
  • Fixtures hung and lamped
  • Terminals torqued
  • GFCI / AFCI tested
  • Panel directory typed
  • Electrical final passed

HVAC Condensers, Grilles & CommissioningHVAC

  • Condensers set and charged
  • Grilles and registers installed
  • Static pressure measured
  • Airflow balanced
  • Condensate protection verified
  • Start-up report filed

Municipal Final Inspections & Certificate of OccupancyBuilder / Super · Inspections

  • All trade finals passed
  • Energy certificate posted
  • Egress and guard dimensions verified
  • Alarms tested
  • Grading release obtained
  • Certificate of Occupancy in hand

QA Punch List & Final CleanBuilder / Super

  • Builder punch complete
  • Trades returned and verified
  • Second verification punch clean
  • Final detail clean done
  • House locked and keyed

Homeowner Orientation & Keys HandoverBuilder / Super

  • Systems orientation completed
  • Documents and warranties delivered
  • Paint and finish schedule provided
  • Utilities transferred
  • Keys, remotes, and codes handed over
  • Warranty visits scheduled