2

Earthwork & Foundation

Dirt work is geometry. Get it wrong and every trade after pays.

Typical duration: 3–6 weeks
5 steps
0/23 complete
12–5 days

Clearing, Erosion Control & Building Stakeout

Clear only what you must, protect the site, and stake the house precisely.

Earthwork
Survey & Engineering

Prerequisites & handoff

  • Permit issued
  • Tree protection plan
  • Utility locates (811) complete

Critical measurements & tolerances

  • Offset stakes set 4'–10' outside the building line so they survive excavation
  • Benchmark elevation established on a permanent object; finished floor elevation noted on it
  • Silt fence trenched 6" into soil, posts max 6' on center

Permits & inspection milestones

  • 811 locate ticket active
  • Erosion control inspection

Field tips & tricks

  • Never let the excavator pull the survey pins. Transfer to offset hubs first and paint them orange.
  • Strip and stockpile topsoil separately — you will want it for final grade and it is expensive to buy back.
  • Build the construction entrance with 3" clean rock before the first concrete truck, or you'll be pressure-washing the street all job.

Reference documents

View in library →

Field checklist

0 / 5 complete
  • 811 locates marked
  • Silt fence and inlet protection in
  • Rock construction entrance built
  • Topsoil stockpiled
  • Offset stakes and benchmark set
23–7 days

Excavation, Pad Build & Compaction

Cut and fill to subgrade, then build engineered fill to design density.

Earthwork

Prerequisites & handoff

  • Stakeout complete
  • Geotech recommendations in hand

Critical measurements & tolerances

  • Fill placed in lifts no thicker than 8" loose
  • Compaction target typically 95% modified Proctor under slabs and footings
  • Over-excavate 1'–2' beyond footing edge for form and drain access
  • Pad built 1"–2" high to allow for final trim

Permits & inspection milestones

  • Compaction / density test report from geotech
  • Open-hole observation where required

Field tips & tricks

  • Keep water out. A rained-in hole costs a week; one day of grading a positive drain path out of the pad is cheap insurance.
  • Don't build pad on topsoil or organics. If it springs under the machine, it will not hold a slab.
  • Photograph every lift with a tape in frame. Density reports and photos settle arguments later.

Reference documents

View in library →

Field checklist

0 / 4 complete
  • Cut / fill to subgrade
  • Lifts compacted and tested
  • Density report filed
  • Pad drains away from house
33–5 days

Underground Plumbing & Utility Sleeves

Everything that lives under the slab goes in and gets tested before concrete.

Plumbing
Electrical
Earthwork

Prerequisites & handoff

  • Pad at grade
  • Plumbing layout dimensioned from stakes / forms

Critical measurements & tolerances

  • Drain slope 1/4" per foot for 3" and smaller, 1/8" per foot allowed for 4" and larger
  • Closet flange centerline 12" from finished wall face, 15" min clear to side wall
  • Cleanouts at every 100' of run and at each change of direction over 45°
  • Water lines and conduit sleeved where they penetrate the slab; sleeve 2 pipe sizes larger
  • Min 12" cover on water service, deeper than local frost depth

Permits & inspection milestones

  • Underground plumbing inspection with 10' head water test or air test held per local code
  • Sewer tap / septic connection inspection

Field tips & tricks

  • Measure toilet and shower drains twice off the actual foundation form, not the plan. Concrete does not move.
  • Leave the water test standing while the inspector is on site; refilling a dropped stack in front of them is a fail.
  • Mark every under-slab penetration on the slab with paint and photograph with dimensions — the framer and tile setter will thank you.

Reference documents

View in library →

Field checklist

0 / 4 complete
  • DWV installed to slope
  • Test held and inspected
  • Water service and sleeves placed
  • Penetrations photographed and dimensioned
43–6 days

Footings, Forms & Rebar Inspection

Form, set steel, and pass the reinforcement inspection before any pour.

Concrete

Prerequisites & handoff

  • Utilities in and inspected
  • Pad trimmed to grade

Critical measurements & tolerances

  • Footing width and depth per plan; bottom below local frost depth
  • Rebar cover: 3" against earth, 1.5" in formed edges
  • Lap splices typically 40 bar diameters (about 30" for #5)
  • Anchor bolts 1/2" min, 7" embedment, max 6' on center, within 12" of each plate end and min 4-1/2" from end
  • Diagonals must match within 1/4" to prove the foundation is square

Permits & inspection milestones

  • Footing / rebar (reinforcement) inspection
  • Post-tension tendon inspection where applicable

Field tips & tricks

  • Chair every bar. Steel lying in the dirt provides zero structure and is the most common rebar inspection failure.
  • Snap diagonals before the pour — check the 3-4-5 on every corner. Out-of-square shows up in cabinets nine months later.
  • Set anchor bolts with a template, not by eye, and keep them out of stud and door-opening locations.

Field checklist

0 / 4 complete
  • Forms set to line and elevation
  • Diagonals verified square
  • Steel chaired, lapped, and tied
  • Rebar inspection passed
52–5 days + cure

Vapor Barrier, Slab Pour & Waterproofing

Place the slab or stem wall, then waterproof and drain below grade.

Concrete

Prerequisites & handoff

  • Rebar inspection passed
  • Concrete mix design approved
  • Weather window

Critical measurements & tolerances

  • Vapor retarder min 10 mil, laps 6" and taped, sealed at all penetrations
  • Slab thickness typically 4" min with specified reinforcement
  • Concrete 2,500–4,000 psi per plan; slump per mix design, do not add water at the truck
  • Floor flatness within 1/4" in 10' for finish flooring
  • Foundation drain in min 12" of washed rock, filter fabric wrapped, sloped to daylight or sump
  • Finished grade falls 6" within the first 10' away from the house

Permits & inspection milestones

  • Slab / pre-pour inspection
  • Waterproofing and drain inspection on basements

Field tips & tricks

  • Wet-cure or cure-seal the slab for 7 days. Fast-dried concrete curls and cracks, and the curl telegraphs into tile.
  • Never puncture the vapor barrier for stakes without patching. Ground moisture ruins wood floors two years later.
  • Check flatness with a 10' straightedge before the concrete crew leaves — grinding is cheap that day, brutal later.

Reference documents

View in library →

Field checklist

0 / 6 complete
  • Vapor barrier sealed
  • Pre-pour inspection passed
  • Slab poured and finished flat
  • Cure protected 7 days
  • Waterproofing and drain installed
  • Backfill compacted in lifts