Trade explorer
Pick a trade to see only the steps it owns, in build order — with the conditions that must be met before it mobilizes and the sign-offs it needs before the next crew arrives.
Zoning & Lot Due Diligence
Confirm the lot can legally hold the house you plan to build before spending a dollar on plans.
Prerequisites & handoff
- Recorded deed / title commitment and legal description
- Plat map with easements and utility corridors
- HOA or architectural review guidelines (if applicable)
Critical measurements & tolerances
- Front / side / rear setbacks per zoning district — verify in feet from property line, not from curb
- Max lot coverage and impervious surface percentage
- Max building height, typically measured from average natural grade to mid-point of roof
- Flood zone / base flood elevation (BFE) — finished floor usually required 1'–2' above BFE
Permits & inspection milestones
- Zoning verification letter
- HOA architectural approval
- Variance application if any setback or height is exceeded
Field tips & tricks
- Walk the lot with the plat and a 300' tape before you order plans. Pin corners disappear; iron is truth.
- Look up, not just down: overhead power and tree canopy drive crane and truss-set access.
- Ask the utility provider for available service capacity in writing. 'It's in the street' is not a commitment.
Field checklist
0 / 5 complete- Title / easements reviewed
- Setback envelope drawn on plat
- Flood zone determination pulled
- Utility availability confirmed in writing
- HOA submittal package sent
Geotechnical Report & Boundary Survey
Soil bearing capacity and a stamped survey drive the entire foundation design.
Prerequisites & handoff
- Lot access for drill rig
- Clearing of borehole paths
Critical measurements & tolerances
- Allowable soil bearing pressure (commonly 1,500–3,000 psf) — footing size math depends on it
- Plasticity index / expansive clay potential (PI > 20 usually means post-tension or pier-and-beam)
- Depth to groundwater and to competent bearing strata
- Boundary survey with corner pins and topo at 1' contours
Permits & inspection milestones
- Stamped boundary + topographic survey
- Geotechnical report for plan review
Field tips & tricks
- Order borings before the foundation engineer starts, not after. Redesign costs more than the borings.
- Get spot elevations at all four corners plus the crown of the street — that's your drainage story.
Field checklist
0 / 4 complete- Borings complete
- Geotech report received and forwarded to engineer
- Boundary + topo survey stamped
- Corner pins flagged and protected
Construction Documents & Engineering
Architectural set, structural engineering, energy compliance, and site plan packaged for submittal.
Prerequisites & handoff
- Approved floor plan and elevations
- Geotech report
- Survey
Critical measurements & tolerances
- Design wind speed, exposure category, and seismic design category from the code map
- Energy code compliance path (prescriptive R-values or performance ACH50 target)
- Foundation plan: footing widths, slab thickness, rebar or tendon layout
- Truss / roof loads: dead + live + snow per local amendment
Permits & inspection milestones
- Sealed structural plans
- Energy compliance certificate (e.g. ResCheck or equivalent)
- Site plan / drainage plan
Field tips & tricks
- Have the plumber and HVAC contractor red-line the plan before submittal — plumbing walls and duct chases are cheapest to fix on paper.
- Lock down cabinet and appliance specs early; they set blocking, gas, and electrical rough-in locations.
Reference documents
View in library →- International Residential Code (IRC) — free read · Code reference
- International Energy Conservation Code (IECC) · Code reference
- ACCA Manuals J, S & D · Industry standard
Field checklist
0 / 5 complete- Architectural set complete
- Structural stamped
- Energy compliance done
- Trades reviewed plans
- Plan set printed for field
Permit Submittal, Review & Issuance
Building permit plus the trade permits and pre-construction site protections.
Prerequisites & handoff
- Complete plan set
- Contractor license and insurance on file
- Fees paid
Critical measurements & tolerances
- Impact / tap fees calculated on conditioned square footage
- Silt fence length and inlet protection per erosion control plan
- Temporary power pole distance from final meter location and required clearances
Permits & inspection milestones
- Building permit
- Separate plumbing, electrical, mechanical permits
- Driveway / right-of-way cut permit
- Erosion control (SWPPP) permit and posted notice
- Water / sewer tap or septic permit, well permit
- Temporary power release
Field tips & tricks
- Answer plan-review comments in a single consolidated resubmittal. Drip-feeding responses restarts the review clock.
- Post the permit card and approved plans in a weather-tight box on site day one — a missing card fails inspections.
- Schedule the temp power drop the day the permit is issued; utility lead times outrun your excavator.
Reference documents
View in library →- International Residential Code (IRC) — free read · Code reference
- NFPA 70 National Electrical Code — free access · Code reference
- EPA Stormwater Construction General Permit · Code reference
Field checklist
0 / 5 complete- Permit issued and card posted
- Trade permits pulled
- SWPPP installed and inspected
- Temp power and temp water set
- Portable toilet and dumpster on site
Clearing, Erosion Control & Building Stakeout
Clear only what you must, protect the site, and stake the house precisely.
Prerequisites & handoff
- Permit issued
- Tree protection plan
- Utility locates (811) complete
Critical measurements & tolerances
- Offset stakes set 4'–10' outside the building line so they survive excavation
- Benchmark elevation established on a permanent object; finished floor elevation noted on it
- Silt fence trenched 6" into soil, posts max 6' on center
Permits & inspection milestones
- 811 locate ticket active
- Erosion control inspection
Field tips & tricks
- Never let the excavator pull the survey pins. Transfer to offset hubs first and paint them orange.
- Strip and stockpile topsoil separately — you will want it for final grade and it is expensive to buy back.
- Build the construction entrance with 3" clean rock before the first concrete truck, or you'll be pressure-washing the street all job.
Reference documents
View in library →- EPA Stormwater Construction General Permit · Code reference
- Call 811 Before You Dig · Industry standard
Field checklist
0 / 5 complete- 811 locates marked
- Silt fence and inlet protection in
- Rock construction entrance built
- Topsoil stockpiled
- Offset stakes and benchmark set
Excavation, Pad Build & Compaction
Cut and fill to subgrade, then build engineered fill to design density.
Prerequisites & handoff
- Stakeout complete
- Geotech recommendations in hand
Critical measurements & tolerances
- Fill placed in lifts no thicker than 8" loose
- Compaction target typically 95% modified Proctor under slabs and footings
- Over-excavate 1'–2' beyond footing edge for form and drain access
- Pad built 1"–2" high to allow for final trim
Permits & inspection milestones
- Compaction / density test report from geotech
- Open-hole observation where required
Field tips & tricks
- Keep water out. A rained-in hole costs a week; one day of grading a positive drain path out of the pad is cheap insurance.
- Don't build pad on topsoil or organics. If it springs under the machine, it will not hold a slab.
- Photograph every lift with a tape in frame. Density reports and photos settle arguments later.
Reference documents
View in library →- OSHA Construction Industry Standards (1926) · Code reference
- OSHA Trenching & Excavation Safety · Code reference
- Call 811 Before You Dig · Industry standard
Field checklist
0 / 4 complete- Cut / fill to subgrade
- Lifts compacted and tested
- Density report filed
- Pad drains away from house
Underground Plumbing & Utility Sleeves
Everything that lives under the slab goes in and gets tested before concrete.
Prerequisites & handoff
- Pad at grade
- Plumbing layout dimensioned from stakes / forms
Critical measurements & tolerances
- Drain slope 1/4" per foot for 3" and smaller, 1/8" per foot allowed for 4" and larger
- Closet flange centerline 12" from finished wall face, 15" min clear to side wall
- Cleanouts at every 100' of run and at each change of direction over 45°
- Water lines and conduit sleeved where they penetrate the slab; sleeve 2 pipe sizes larger
- Min 12" cover on water service, deeper than local frost depth
Permits & inspection milestones
- Underground plumbing inspection with 10' head water test or air test held per local code
- Sewer tap / septic connection inspection
Field tips & tricks
- Measure toilet and shower drains twice off the actual foundation form, not the plan. Concrete does not move.
- Leave the water test standing while the inspector is on site; refilling a dropped stack in front of them is a fail.
- Mark every under-slab penetration on the slab with paint and photograph with dimensions — the framer and tile setter will thank you.
Reference documents
View in library →- International Plumbing Code (IPC) · Code reference
- OSHA Construction Industry Standards (1926) · Code reference
- OSHA Trenching & Excavation Safety · Code reference
Field checklist
0 / 4 complete- DWV installed to slope
- Test held and inspected
- Water service and sleeves placed
- Penetrations photographed and dimensioned
Footings, Forms & Rebar Inspection
Form, set steel, and pass the reinforcement inspection before any pour.
Prerequisites & handoff
- Utilities in and inspected
- Pad trimmed to grade
Critical measurements & tolerances
- Footing width and depth per plan; bottom below local frost depth
- Rebar cover: 3" against earth, 1.5" in formed edges
- Lap splices typically 40 bar diameters (about 30" for #5)
- Anchor bolts 1/2" min, 7" embedment, max 6' on center, within 12" of each plate end and min 4-1/2" from end
- Diagonals must match within 1/4" to prove the foundation is square
Permits & inspection milestones
- Footing / rebar (reinforcement) inspection
- Post-tension tendon inspection where applicable
Field tips & tricks
- Chair every bar. Steel lying in the dirt provides zero structure and is the most common rebar inspection failure.
- Snap diagonals before the pour — check the 3-4-5 on every corner. Out-of-square shows up in cabinets nine months later.
- Set anchor bolts with a template, not by eye, and keep them out of stud and door-opening locations.
Reference documents
View in library →- International Residential Code (IRC) — free read · Code reference
- Footing & Rebar Pre-Pour Inspection Form· Inspection form
- Simpson Strong-Tie Connector & Hold-Down Catalog · Install guide
- ACI Concrete Field Reference & Cold/Hot Weather Guides · Industry standard
Field checklist
0 / 4 complete- Forms set to line and elevation
- Diagonals verified square
- Steel chaired, lapped, and tied
- Rebar inspection passed
Vapor Barrier, Slab Pour & Waterproofing
Place the slab or stem wall, then waterproof and drain below grade.
Prerequisites & handoff
- Rebar inspection passed
- Concrete mix design approved
- Weather window
Critical measurements & tolerances
- Vapor retarder min 10 mil, laps 6" and taped, sealed at all penetrations
- Slab thickness typically 4" min with specified reinforcement
- Concrete 2,500–4,000 psi per plan; slump per mix design, do not add water at the truck
- Floor flatness within 1/4" in 10' for finish flooring
- Foundation drain in min 12" of washed rock, filter fabric wrapped, sloped to daylight or sump
- Finished grade falls 6" within the first 10' away from the house
Permits & inspection milestones
- Slab / pre-pour inspection
- Waterproofing and drain inspection on basements
Field tips & tricks
- Wet-cure or cure-seal the slab for 7 days. Fast-dried concrete curls and cracks, and the curl telegraphs into tile.
- Never puncture the vapor barrier for stakes without patching. Ground moisture ruins wood floors two years later.
- Check flatness with a 10' straightedge before the concrete crew leaves — grinding is cheap that day, brutal later.
Reference documents
View in library →- Footing & Rebar Pre-Pour Inspection Form· Inspection form
- Stego Wrap Vapor Barrier Installation · Install guide
- ACI Concrete Field Reference & Cold/Hot Weather Guides · Industry standard
Field checklist
0 / 6 complete- Vapor barrier sealed
- Pre-pour inspection passed
- Slab poured and finished flat
- Cure protected 7 days
- Waterproofing and drain installed
- Backfill compacted in lifts
Sill Plates, Wall Framing & Layout
Plate layout, wall framing, openings, and blocking that every later trade depends on.
Prerequisites & handoff
- Slab cured and swept
- Anchor bolts verified
- Approved plans on site
Critical measurements & tolerances
- Pressure-treated sill plate with sill sealer / termite barrier on all concrete contact
- Studs 16" on center standard, 24" allowed on some non-bearing and advanced-framing walls
- Walls plumb within 1/4" over 8' and straight within 1/4" in 10'
- Rough openings: standard interior door RO = door width + 2", height + 2-1/2"; verify per manufacturer
- Header sizing per span table; king and jack stud count per plan
- Notching / boring limits: bore max 40% of stud depth, notch max 25%, hole min 5/8" from edge
- Tub / shower blocking at 32"–34" for grab bars, cabinet blocking at 54" and 84" for uppers
Permits & inspection milestones
- Shear wall / hold-down inspection where required before sheathing is covered
Field tips & tricks
- Crown every stud the same direction and cull the bananas. Drywall shows every bowed stud under raking light.
- String-line the top plate of long walls before sheathing. Straight walls make cabinets and trim fast.
- Add backing for towel bars, TVs, closet shelves and handrails now — photograph it with a tape for the drywall punch.
Reference documents
View in library →- International Residential Code (IRC) — free read · Code reference
- Framing / Shear Wall Inspection Form· Inspection form
- APA Engineered Wood Construction Guide · Install guide
Field checklist
0 / 5 complete- Sill sealer and PT plates set
- Walls framed, plumb, and straight
- Headers per plan
- Rough openings verified against door / window schedule
- Blocking and backing installed and photographed
Shear Walls, Straps & Hold-downs
The lateral system: sheathing, nailing patterns, and the connectors that resist wind and seismic load.
Prerequisites & handoff
- Walls framed and braced
- Structural sheet showing shear schedule
Critical measurements & tolerances
- Nailing per shear schedule, commonly 8d at 6" edge / 12" field; 4" or 3" edge for high-load panels
- Nails set flush — overdriven more than 1/16" loses shear capacity and fails inspection
- Panel edge gap 1/8" for expansion
- Hold-down anchors torqued and squarely bearing; strap nailing 100% filled
Permits & inspection milestones
- Framing / shear inspection
- Special inspection where the structural sheet calls for it
Field tips & tricks
- Set the nail gun pressure with a test panel each morning. Overdriven nails are the #1 shear failure.
- Fill every hole in every strap. A half-nailed strap is worth nothing to an engineer or inspector.
Reference documents
View in library →- International Residential Code (IRC) — free read · Code reference
- Framing / Shear Wall Inspection Form· Inspection form
- Simpson Strong-Tie Connector & Hold-Down Catalog · Install guide
- APA Engineered Wood Construction Guide · Install guide
Field checklist
0 / 4 complete- Sheathing nailing verified
- Hold-downs installed and torqued
- Straps fully nailed
- Shear inspection passed
Floor System, Roof Trusses & Sheathing
Set the floor and roof structure, brace it permanently, and sheathe.
Prerequisites & handoff
- Walls plumb and braced
- Truss package approved by engineer
- Crane access confirmed
Critical measurements & tolerances
- Subfloor glued and screwed; deflection / squeak-free, flat within 1/4" in 10'
- Truss bearing min 3" on wood, per truss drawing; never cut or notch a truss
- Permanent lateral bracing and web bracing exactly per truss engineering
- Roof sheathing H-clips where specified, 1/8" panel gap
- Attic access min 22" x 30" with 30" headroom above
Permits & inspection milestones
- Framing inspection including truss bracing
Field tips & tricks
- Keep the stamped truss drawings on site. Inspectors check bracing against them, not against habit.
- Any truss modification needs written engineering. Field-cutting a web is a rebuild, not a repair.
Reference documents
View in library →- OSHA Construction Industry Standards (1926) · Code reference
- Framing / Shear Wall Inspection Form· Inspection form
- Simpson Strong-Tie Connector & Hold-Down Catalog · Install guide
- APA Engineered Wood Construction Guide · Install guide
- BCSI Truss Handling, Installing & Bracing · Install guide
Field checklist
0 / 4 complete- Floor system set, glued, screwed
- Trusses set and braced per drawings
- Roof sheathed and clipped
- Truss drawings on site
Roof Dry-in, Windows & Exterior Doors
Get the house watertight — the milestone that lets interior trades start.
Prerequisites & handoff
- Roof sheathed
- Windows on site and inspected for damage
Critical measurements & tolerances
- Underlayment laps 2" horizontal, 4" vertical minimum; ice barrier from eave to 24" inside the warm wall in cold climates
- Valley and step flashing min 4" each side; kickout flashing at every roof-to-wall termination
- Window flashing sequence: sill pan first, jambs, then head flashing over the WRB
- WRB laps shingle-style: upper course over lower, 6" min vertical laps
Permits & inspection milestones
- Weather barrier / window flashing inspection in many jurisdictions
Field tips & tricks
- The kickout flashing is the single cheapest part on the job and the cause of the most expensive wall rot. Never skip it.
- Shim windows at the sill only at bearing points, and never through the sill pan.
- Flash sill pans before the window, tape jambs over the flange, leave the head lap under the WRB — water always wins arguments about order.
Reference documents
View in library →- OSHA Construction Industry Standards (1926) · Code reference
- GAF Shingle Installation Instructions · Install guide
- DuPont Tyvek WRB & Flashing Installation Guide · Install guide
- Window Installation Instructions (Pella) · Install guide
Field checklist
0 / 5 complete- Roof dried in
- WRB installed shingle-lapped
- Windows set plumb, level, flashed
- Exterior doors set and pan-flashed
- Kickouts installed
Plumbing Rough-in
DWV, vents, water distribution, and tub / shower sets, pressure-tested.
Prerequisites & handoff
- House dried in
- Framing complete
- Fixture and cabinet specs final
Critical measurements & tolerances
- Water closet rough 12" from finished wall, 15" min clear to side obstruction, 21" clear in front
- Lavatory drain at ~18"–20" AFF, supplies 20"–22" AFF unless vanity dictates otherwise
- Shower valve 42"–48" AFF, shower head 78"–80" AFF, tub spout 4"–6" above rim
- Vent within developed length limits per code table; vent stacks min 6" above roof and 10' from any openable window
- Trap arm slope 1/4" per foot; no S-traps
- Pressure test: 100 psi air or water held per local code during inspection
- Protect pipe within 1-1/4" of stud face with 16-gauge nail plates
Permits & inspection milestones
- Plumbing rough-in inspection with test held
- Gas piping pressure test
Field tips & tricks
- Set the tub and shower pan during rough — then protect it with plywood, not cardboard, for the rest of the job.
- Nail-plate everything. A drywall screw through PEX found at trim-out means opening finished walls.
- Dry-fit the vanity and toilet locations against the actual cabinet shop drawing before you glue anything.
Reference documents
View in library →- International Plumbing Code (IPC) · Code reference
- MEP Rough-in Pre-Drywall Inspection Form· Inspection form
- Uponor PEX Plumbing Design & Installation Manual · Install guide
- Schluter KERDI Shower System Installation · Install guide
- Moen Faucet & Valve Installation Instructions · Install guide
Field checklist
0 / 5 complete- DWV and vents complete
- Water lines run and manifolded
- Tub / shower pans set and protected
- Nail plates installed
- Test held, inspection passed
HVAC Ductwork & Equipment Rough
Load-calculated duct system, equipment platforms, flues, and refrigerant lines.
Prerequisites & handoff
- Plumbing rough in (plumbing generally wins wall space)
- Manual J / D / S complete
Critical measurements & tolerances
- System sized from Manual J load, not rule of thumb; duct sized by Manual D
- Supply / return sizing to keep static pressure at or under equipment spec (typically 0.5" w.c. total external)
- Flexible duct pulled tight, supported every 4', no radius tighter than one duct diameter
- Return path for every closed room — door undercut, transfer grille, or jump duct
- Dryer vent max length per manufacturer (commonly 35' less 5' per 90° elbow), rigid metal only
- Combustion appliance clearances and vent terminations per listing
Permits & inspection milestones
- Mechanical rough-in inspection
- Duct leakage test (often Qn ≤ 4% of floor area)
Field tips & tricks
- Kinked flex duct is invisible after drywall and shows up as a hot bedroom forever. Walk every run with a flashlight.
- Mastic, not tape, on every joint and boot. Foil tape alone loses the duct-leakage test.
- Coordinate the return chase with the framer before drywall — a stolen chase means soffits in the finished house.
Reference documents
View in library →- International Energy Conservation Code (IECC) · Code reference
- MEP Rough-in Pre-Drywall Inspection Form· Inspection form
- ACCA Manuals J, S & D · Industry standard
Field checklist
0 / 6 complete- Manual J / D / S on file
- Trunks and branches installed and supported
- Boots sealed with mastic
- Return paths for all rooms
- Line sets and flues installed
- Rough inspection passed
Electrical Rough-in & Home Runs
Panel, circuits, boxes, and device locations set to code and to the lighting plan.
Prerequisites & handoff
- Plumbing and HVAC rough (electrical routes around them)
- Lighting and appliance schedule final
Critical measurements & tolerances
- Receptacle height typically 12"–16" to box bottom; switches 42"–48" to center
- Kitchen counters: receptacle within 24" of any point along the wall line, no point more than 24" from an outlet; min two 20A small-appliance circuits
- General rooms: no point along a wall more than 6' from a receptacle; walls 2' or wider get one
- Box fill calculated; cables stapled within 8" of box and every 4-1/2'
- Bored holes centered in stud, min 1-1/4" from face or nail-plated
- AFCI protection on most living-area circuits; GFCI at kitchen, bath, laundry, garage, exterior, and within 6' of any sink
- Panel: 30" wide x 36" deep clear working space, 6'-7" headroom, breaker handles max 6'-7" AFF
- Smoke alarms in each bedroom, outside each sleeping area, each level; min 3' from supply registers and bath doors
Permits & inspection milestones
- Electrical rough-in inspection
- Service / meter release from utility
Field tips & tricks
- Walk the lighting plan with the homeowner at rough, in the actual rooms, with switch boxes nailed. Changes cost $20 now, $2,000 later.
- Set box depth for the finished wall thickness. Boxes recessed behind drywall are a code violation and a tedious fix.
- Leave a labeled 12"-tail and a plan mark-up photo of every home run. Trim-out gets twice as fast.
Reference documents
View in library →- NFPA 70 National Electrical Code — free access · Code reference
- MEP Rough-in Pre-Drywall Inspection Form· Inspection form
- Eaton Load Center & Breaker Instructions · Install guide
Field checklist
0 / 6 complete- Panel set and grounded
- Boxes set to depth and height
- Home runs pulled and labeled
- AFCI / GFCI circuits mapped
- Smoke / CO locations verified
- Rough inspection passed
Low Voltage, Security & Pre-wire
Data, TV, audio, cameras, doorbell, and network head-end pre-wire.
Prerequisites & handoff
- Electrical rough substantially complete
- AV / network plan
Critical measurements & tolerances
- Keep low voltage min 12" parallel separation from line voltage; cross at 90° only
- Cat6 max run 295' (100 m) including patch cords
- TV outlets: box + conduit sleeve behind each display; 60"–66" AFF for wall-mounts
- Network head-end: dedicated receptacle, ventilation, and a labeled panel
Permits & inspection milestones
- Low-voltage permit where required; usually inspected with electrical rough
Field tips & tricks
- Pull a spare conduit from head-end to attic and to the media wall. Future you will pay real money for it.
- Label both ends of every cable with a printed tag before drywall. Toning 40 unlabeled drops is a lost day.
Reference documents
View in library →- MEP Rough-in Pre-Drywall Inspection Form· Inspection form
- Structured Cabling Best Practices (TIA-570) · Industry standard
Field checklist
0 / 5 complete- Data / coax pulled and labeled
- Camera and doorbell runs in
- Speaker wire and backboxes set
- Head-end location powered
- Spare conduits installed
Pre-Drywall Multi-Trade Walk & Framing Inspection
Coordinated sign-off from framing, plumbing, mechanical, electrical, and the building official.
Prerequisites & handoff
- All rough-ins complete and tested
- Fire blocking and draft stopping installed
Critical measurements & tolerances
- Fire blocking at all concealed vertical/horizontal intersections and max 10' in stud cavities
- Draft stopping in floor / attic assemblies over 1,000 sq ft where required
- Penetrations through top and bottom plates sealed
- Notch / bore repairs plated and verified
Permits & inspection milestones
- Framing inspection
- Combined rough or 4-way inspection where offered
- Engineer letter for any field-modified structure
Field tips & tricks
- Do your own punch walk with a flashlight the day before the inspector. You will find 20 items; they only need one to fail you.
- Photograph every wall bay before insulation. The best as-built documentation you will ever have costs 30 minutes.
- Invite the homeowner to a pre-drywall walk — it is the last easy chance for changes and it builds enormous trust.
Reference documents
View in library →- International Residential Code (IRC) — free read · Code reference
- Framing / Shear Wall Inspection Form· Inspection form
- MEP Rough-in Pre-Drywall Inspection Form· Inspection form
Field checklist
0 / 5 complete- Fire blocking / draft stopping complete
- All trade rough inspections passed
- Framing inspection passed
- Wall bays photographed
- Homeowner pre-drywall walk done
Air Sealing, Insulation & Blower-Door Prep
Seal the envelope, then insulate to the energy code and verify by test.
Prerequisites & handoff
- All rough inspections passed
- Windows and doors installed
Critical measurements & tolerances
- Typical code targets: R-13 to R-21 walls, R-38 to R-60 ceilings, per climate zone
- Blower-door target commonly ≤ 3.0 ACH50 (climate zones 3–8) or ≤ 5.0 ACH50 (zones 1–2)
- Insulation installed to Grade I: full contact, split around wiring, no compression or voids
- Baffles maintain min 1" clear vent space at eaves; attic vent net free area 1:150 (or 1:300 with balanced vents)
- Fire caulk rated penetrations; foam-seal all top plate, rim joist, and can-light penetrations
Permits & inspection milestones
- Insulation inspection before drywall
- Blower-door test and energy compliance report
Field tips & tricks
- Air seal before insulation, not after. Insulation without air sealing is a filter, not a barrier.
- Split batts around wiring and plumbing instead of squashing them — compression is the most common Grade I failure.
- Run a pre-test blower door before drywall so leaks are still reachable. Fixing 5 ACH after paint is misery.
Reference documents
View in library →- International Energy Conservation Code (IECC) · Code reference
- Insulation & Air-Sealing Inspection Form· Inspection form
- RESNET HERS & Blower-Door Testing Standards · Industry standard
- Owens Corning Insulation Installation Guides · Install guide
Field checklist
0 / 6 complete- Top plates and rim joists sealed
- Penetrations fire-caulked
- Baffles installed
- Insulation to spec, Grade I
- Pre-drywall blower door run
- Insulation inspection passed
Drywall Hang, Tape, Texture & Prime
Board the house, finish the joints to the specified level, and prime.
Prerequisites & handoff
- Insulation inspection passed
- House dry and conditioned
Critical measurements & tolerances
- 1/2" board typical walls; 5/8" Type X at garage / house separation and where fire-rated
- Ceilings 5/8" or 1/2" sag-resistant at 24" framing spacing
- Screws max 16" on center on ceilings, 16" walls (12" for fire-rated per listing); set dimple, no paper tear
- 1/2" gap above floor to avoid wicking moisture
- Cement board or approved membrane in wet areas — never paper-faced gypsum in a shower
- Finish level: Level 4 typical for flat paint, Level 5 for gloss or raking light
- Maintain 50–80°F and ventilation during taping and drying
Permits & inspection milestones
- Fire-rated assembly inspection at garage separation where required
Field tips & tricks
- Prime before you inspect. Raw mud lies; primer shows every ridge and screw pop.
- Run a bright work light down each wall at a low angle before paint — catching flaws now costs minutes, later costs furniture moves.
- Control humidity. Fast heat with no ventilation cracks joints and bubbles tape.
Reference documents
View in library →- GA-216 Application of Gypsum Panel Products · Industry standard
- USG Gypsum Construction Handbook · Install guide
- Sherwin-Williams Surface Prep & Application Guide · Install guide
Field checklist
0 / 5 complete- Board hung and screwed to pattern
- Fire-rated assemblies correct
- Taped and textured to spec level
- Primed
- Light-raked and touched up
Interior Doors, Trim & Stairs
Hang doors, run casing and base, and build out stairs and railings.
Prerequisites & handoff
- Drywall finished and primed
- Flooring thickness known
Critical measurements & tolerances
- Door reveal 1/8" consistent at head and hinge side; 3/16" at strike typical
- Undercut doors for flooring plus HVAC return path (commonly 3/4"–1")
- Stairs: rise max 7-3/4", run min 10", variation between the largest and smallest within a flight max 3/8"
- Handrail 34"–38" above tread nosing; guardrail 36" min with max 4" sphere opening
- Base and casing joints coped, not just mitered, on inside corners
Permits & inspection milestones
- Stair / guardrail dimensions verified at final inspection
Field tips & tricks
- Shim the hinge jamb plumb in both planes before you touch the latch side — every reveal problem starts there.
- Glue miters and pin them; caulk hides nothing on a stained trim package.
- Measure the actual stair rise after flooring is specified, not before. A 3/8" miss fails inspection.
Reference documents
View in library →- TCNA Handbook for Ceramic, Glass & Stone Tile · Industry standard
- Sherwin-Williams Surface Prep & Application Guide · Install guide
Field checklist
0 / 5 complete- Doors hung, reveals even, latching
- Casing and base installed
- Stair rise / run verified
- Handrails and guards to height
- Caulked and puttied for paint
Cabinets, Countertops & Tile
Set casework level, template tops, and install tile and flooring.
Prerequisites & handoff
- Trim and paint substantially complete
- Appliance specs confirmed
- Floor flat and dry
Critical measurements & tolerances
- Base cabinets 34-1/2" high, counter at 36"; uppers 18" above counter typical
- Cabinets level within 1/8" across the run and shimmed to a laser line, not to the floor
- Slab template only after cabinets are set and fastened
- Tile substrate deflection max L/360 (L/720 for natural stone)
- Waterproof shower pan pre-slope 1/4" per foot, flood test 24 hours before tile
- Tile lippage: keep under 1/32" for joints under 1/4"; back-butter large format for 95% coverage in wet areas
- Wood flooring: acclimate to site, subfloor moisture within manufacturer spec (commonly ≤ 12% and within 4% of the flooring)
Permits & inspection milestones
- Shower pan flood test inspection in many jurisdictions
Field tips & tricks
- Laser a level line around the whole kitchen first and hang everything to it. Chasing an out-of-level floor ruins a run.
- Flood test the shower pan for 24 hours and photograph it with a date. It is the cheapest callback insurance on the job.
- Check the appliance cut sheets against the opening before the tops are templated. A 1/8" fridge opening miss is a new cabinet.
Reference documents
View in library →- TCNA Handbook for Ceramic, Glass & Stone Tile · Industry standard
- Schluter KERDI Shower System Installation · Install guide
- KCMA Cabinet Installation Guidelines · Install guide
Field checklist
0 / 6 complete- Cabinets set, level, fastened to blocking
- Appliance openings verified
- Tops templated and installed
- Shower pan flood tested
- Tile set, lippage checked
- Flooring moisture tested and installed
Siding, Stucco or Masonry Veneer
Install the cladding system with a working drainage plane behind it.
Prerequisites & handoff
- WRB and flashings complete and inspected
- Windows flashed
Critical measurements & tolerances
- Min 6" clearance from siding to finished grade, 2" above hard surfaces such as walks and decks
- Lap siding: manufacturer's minimum overlap (commonly 1-1/4"), nails into studs, no face-nailing where prohibited
- Stucco: 3-coat over two layers of WRB, total nominal 7/8" thickness, weep screed at base, control joints per area limits
- Masonry veneer: 1" min air space, weeps max 33" on center at the base course, ties every 16" vertical / 24" horizontal
- Sealant joints at all dissimilar materials with backer rod, joint depth roughly half the width
Permits & inspection milestones
- Lath / weather barrier inspection before stucco scratch coat
- Cladding inspection where required
Field tips & tricks
- Never let stucco or siding bridge the weep screed to grade — it wicks water straight into the framing.
- Keep the drainage plane continuous. Every penetration gets flashed or sealed the same day it's cut.
- Confirm the brick ledge air space is actually clear of mortar droppings before you close the wall.
Reference documents
View in library →- DuPont Tyvek WRB & Flashing Installation Guide · Install guide
- James Hardie Siding Installation Guide · Install guide
Field checklist
0 / 5 complete- Lath / WRB inspected
- Cladding installed to spec
- Weeps and air space clear
- Clearances to grade verified
- Penetrations flashed and sealed
Flatwork, Grading, Gutters & Drainage
Driveway, walks, final grade, and roof water routed away from the house.
Prerequisites & handoff
- Cladding complete
- Utilities trenches backfilled and compacted
Critical measurements & tolerances
- Driveway slab typically 4"–6" thick with control joints at 8'–12' spacing (max ~30x slab thickness)
- Walk cross-slope max 2% for accessibility comfort; slope away from the house
- Final grade falls min 6" in the first 10' from the foundation
- Gutters: downspout for roughly every 600–800 sq ft of roof, discharge min 5'–10' from the foundation
- Backfill compacted in lifts to prevent settling at the foundation
Permits & inspection milestones
- Right-of-way / driveway approach inspection
- Final grading and drainage inspection
Field tips & tricks
- Saw or tool control joints within 6–12 hours of the pour. Late joints mean random cracks.
- Extend downspouts before the first storm. Water at the foundation is the most common warranty claim in year one.
- Never pour flatwork tight against siding; keep the required clearance and use an expansion joint at the house.
Reference documents
View in library →- Call 811 Before You Dig · Industry standard
- ACI Concrete Field Reference & Cold/Hot Weather Guides · Industry standard
Field checklist
0 / 5 complete- Sub-base compacted
- Flatwork poured and jointed
- Final grade sloped away
- Gutters and extensions installed
- Drainage verified with a hose test
Plumbing Fixtures & Water Heater Start-up
Set fixtures, trim valves, connect appliances, and commission hot water.
Prerequisites & handoff
- Tile and flooring complete
- Countertops installed
- Water service live
Critical measurements & tolerances
- Water heater T&P discharge full size, downhill, terminating 6"–24" above grade or drain pan
- Water heater set at 120°F to reduce scald risk
- Expansion tank on closed systems; pressure-reducing valve where static pressure exceeds 80 psi
- Toilet bolted to flange with new wax or waxless seal, closet ring at or slightly above finish floor
- Traps and tailpieces with no flat sections; dishwasher high loop or air gap
Permits & inspection milestones
- Plumbing final inspection
- Backflow / cross-connection test where applicable
Field tips & tricks
- Fill and run every fixture, then check under the sink with a dry paper towel 20 minutes later. That towel finds leaks eyes do not.
- Photograph angle stop and shutoff locations for the homeowner binder.
- Set the water heater temperature and label the main shutoff before the walkthrough — it always gets asked about.
Reference documents
View in library →- International Plumbing Code (IPC) · Code reference
- Moen Faucet & Valve Installation Instructions · Install guide
Field checklist
0 / 5 complete- Fixtures set and sealed
- Water heater installed and started
- PRV / expansion tank verified
- Appliance connections made
- Leak check documented
Electrical Trim, Devices & Panel Labeling
Devices, fixtures, panel schedule, and full circuit testing.
Prerequisites & handoff
- Paint complete
- Fixtures on site
- Meter released
Critical measurements & tolerances
- Devices plumb and flush to plate, no gaps over 1/8"
- Torque every terminal to the listed value — a torque screwdriver is now expected by many inspectors
- Panel directory legibly labeled by circuit and room
- GFCI / AFCI test-and-reset verified on every protected circuit
- Exterior and wet-location devices with weather-resistant, in-use covers
Permits & inspection milestones
- Electrical final inspection
- Utility permanent power release
Field tips & tricks
- Test every receptacle with a tester and every GFCI with its button. Inspectors pick randomly and one miss reschedules a day.
- Vacuum and wipe the panel interior. A clean panel with a typed directory sets the tone for the whole final inspection.
Reference documents
View in library →- NFPA 70 National Electrical Code — free access · Code reference
- Eaton Load Center & Breaker Instructions · Install guide
Field checklist
0 / 6 complete- Devices and plates installed
- Fixtures hung and lamped
- Terminals torqued
- GFCI / AFCI tested
- Panel directory typed
- Electrical final passed
HVAC Condensers, Grilles & Commissioning
Set outdoor units, register the system, balance airflow, and document performance.
Prerequisites & handoff
- Flatwork / pad poured
- Power available
- Filters and grilles on site
Critical measurements & tolerances
- Condenser on level pad, min 12"–24" service clearance per manufacturer, above flood elevation
- Refrigerant charge verified by subcooling / superheat to manufacturer target
- Total external static pressure measured and within equipment rating
- Airflow balanced to Manual D design CFM per room, typically within 10%
- Condensate primary plus secondary pan and float switch; trap and slope 1/8" per foot
- Thermostat 48"–60" AFF, away from supply registers and direct sun
Permits & inspection milestones
- Mechanical final inspection
- Duct leakage and system commissioning report
Field tips & tricks
- Document static pressure, charge, and room CFM in a start-up report. It settles comfort complaints and supports the warranty.
- Pour or set the condenser pad level. A tilted unit is a service call and an oil-return problem.
- Replace the filter after drywall dust. Commissioning through a loaded filter gives you fiction, not data.
Reference documents
View in library →- RESNET HERS & Blower-Door Testing Standards · Industry standard
- Carrier Residential Equipment Installation Instructions · Install guide
Field checklist
0 / 6 complete- Condensers set and charged
- Grilles and registers installed
- Static pressure measured
- Airflow balanced
- Condensate protection verified
- Start-up report filed
Municipal Final Inspections & Certificate of Occupancy
All trade finals, energy verification, and the CO that makes the house legally habitable.
Prerequisites & handoff
- All trade finals scheduled
- Site clean and safe
- Address numbers posted
Critical measurements & tolerances
- Blower-door and duct-leakage results at or under code targets, documented
- Egress windows: min 5.7 sq ft net clear opening (5.0 at grade floor), 24" clear height, 20" clear width, sill max 44" AFF
- Guardrails at any walking surface more than 30" above grade; 4" sphere rule
- Smoke / CO alarms interconnected and functioning
- Handrail graspability and continuity along the full flight
- Address numbers min 4" high, contrasting, visible from the street
Permits & inspection milestones
- Building final inspection
- Plumbing / mechanical / electrical finals
- Energy compliance certificate posted at the panel
- Final grading and erosion control release
- Certificate of Occupancy issued
Field tips & tricks
- Run your own mock final with the code checklist two days before the inspector. Fix the five items you find quietly.
- Have the permit card, approved plans, truss drawings, energy certificate and test reports in one binder on the counter.
- Take the SWPPP down only after final grading release — an early removal can hold your CO.
Reference documents
View in library →- International Residential Code (IRC) — free read · Code reference
- International Energy Conservation Code (IECC) · Code reference
- Final Inspection & CO Readiness Form· Inspection form
- RESNET HERS & Blower-Door Testing Standards · Industry standard
Field checklist
0 / 6 complete- All trade finals passed
- Energy certificate posted
- Egress and guard dimensions verified
- Alarms tested
- Grading release obtained
- Certificate of Occupancy in hand
QA Punch List & Final Clean
Builder punch, trade returns, verification punch, then detail clean.
Prerequisites & handoff
- CO issued or pending
- All trades notified of punch window
Critical measurements & tolerances
- Doors and drawers operate and align; reveals consistent
- Paint inspected under raking light and normal room lighting from 6' distance
- Every window and door opens, locks, and weather-strips
- All fixtures, outlets, and switches operated once and logged
- Grout and caulk lines continuous at all wet-area changes of plane
Permits & inspection milestones
- None — internal quality gate
Field tips & tricks
- Punch room by room, clockwise, ceiling to floor. Blue tape everything and photograph each tag into the punch log.
- Hold trade retainage until punch items are verified, not just reported complete.
- Do the final clean after punch, then lock the house. One trade walking through undoes a $900 clean.
Reference documents
View in library →- QA Punch List & Homeowner Walkthrough Form· Inspection form
- Sherwin-Williams Surface Prep & Application Guide · Install guide
- NAHB Residential Construction Performance Guidelines · Industry standard
Field checklist
0 / 5 complete- Builder punch complete
- Trades returned and verified
- Second verification punch clean
- Final detail clean done
- House locked and keyed
Homeowner Orientation & Keys Handover
Walk the house, train the owner on systems, deliver documents, hand over keys.
Prerequisites & handoff
- CO issued
- Punch closed
- Warranty package assembled
Critical measurements & tolerances
- Demonstrate: main water shutoff, gas shutoff, panel and breakers, thermostat, GFCI reset, irrigation timer
- Filter sizes and replacement intervals written down
- Warranty terms: typically 1 year workmanship, 2 years systems, 10 years structural
Permits & inspection milestones
- Certificate of Occupancy delivered to homeowner
- Utility accounts transferred
Field tips & tricks
- Record the orientation walk on video and send it to the homeowner. It eliminates half of the year-one calls.
- Deliver a binder and a digital folder: CO, permits, manuals, warranties, paint colors with sheens, and every test report.
- Schedule the 30-day and 11-month warranty visits at the handover while everyone is happy.
Reference documents
View in library →- QA Punch List & Homeowner Walkthrough Form· Inspection form
- NAHB Residential Construction Performance Guidelines · Industry standard
Field checklist
0 / 6 complete- Systems orientation completed
- Documents and warranties delivered
- Paint and finish schedule provided
- Utilities transferred
- Keys, remotes, and codes handed over
- Warranty visits scheduled