MEP Rough-ins

Plumbing, HVAC, electrical and low voltage race inside the walls — sequence them or pay twice.

Typical duration: 2–4 weeks
4 steps
0/22 complete
14–7 days

Plumbing Rough-in

DWV, vents, water distribution, and tub / shower sets, pressure-tested.

Plumbing

Prerequisites & handoff

  • House dried in
  • Framing complete
  • Fixture and cabinet specs final

Critical measurements & tolerances

  • Water closet rough 12" from finished wall, 15" min clear to side obstruction, 21" clear in front
  • Lavatory drain at ~18"–20" AFF, supplies 20"–22" AFF unless vanity dictates otherwise
  • Shower valve 42"–48" AFF, shower head 78"–80" AFF, tub spout 4"–6" above rim
  • Vent within developed length limits per code table; vent stacks min 6" above roof and 10' from any openable window
  • Trap arm slope 1/4" per foot; no S-traps
  • Pressure test: 100 psi air or water held per local code during inspection
  • Protect pipe within 1-1/4" of stud face with 16-gauge nail plates

Permits & inspection milestones

  • Plumbing rough-in inspection with test held
  • Gas piping pressure test

Field tips & tricks

  • Set the tub and shower pan during rough — then protect it with plywood, not cardboard, for the rest of the job.
  • Nail-plate everything. A drywall screw through PEX found at trim-out means opening finished walls.
  • Dry-fit the vanity and toilet locations against the actual cabinet shop drawing before you glue anything.

Field checklist

0 / 5 complete
  • DWV and vents complete
  • Water lines run and manifolded
  • Tub / shower pans set and protected
  • Nail plates installed
  • Test held, inspection passed
24–7 days

HVAC Ductwork & Equipment Rough

Load-calculated duct system, equipment platforms, flues, and refrigerant lines.

HVAC

Prerequisites & handoff

  • Plumbing rough in (plumbing generally wins wall space)
  • Manual J / D / S complete

Critical measurements & tolerances

  • System sized from Manual J load, not rule of thumb; duct sized by Manual D
  • Supply / return sizing to keep static pressure at or under equipment spec (typically 0.5" w.c. total external)
  • Flexible duct pulled tight, supported every 4', no radius tighter than one duct diameter
  • Return path for every closed room — door undercut, transfer grille, or jump duct
  • Dryer vent max length per manufacturer (commonly 35' less 5' per 90° elbow), rigid metal only
  • Combustion appliance clearances and vent terminations per listing

Permits & inspection milestones

  • Mechanical rough-in inspection
  • Duct leakage test (often Qn ≤ 4% of floor area)

Field tips & tricks

  • Kinked flex duct is invisible after drywall and shows up as a hot bedroom forever. Walk every run with a flashlight.
  • Mastic, not tape, on every joint and boot. Foil tape alone loses the duct-leakage test.
  • Coordinate the return chase with the framer before drywall — a stolen chase means soffits in the finished house.

Reference documents

View in library →

Field checklist

0 / 6 complete
  • Manual J / D / S on file
  • Trunks and branches installed and supported
  • Boots sealed with mastic
  • Return paths for all rooms
  • Line sets and flues installed
  • Rough inspection passed
34–7 days

Electrical Rough-in & Home Runs

Panel, circuits, boxes, and device locations set to code and to the lighting plan.

Electrical

Prerequisites & handoff

  • Plumbing and HVAC rough (electrical routes around them)
  • Lighting and appliance schedule final

Critical measurements & tolerances

  • Receptacle height typically 12"–16" to box bottom; switches 42"–48" to center
  • Kitchen counters: receptacle within 24" of any point along the wall line, no point more than 24" from an outlet; min two 20A small-appliance circuits
  • General rooms: no point along a wall more than 6' from a receptacle; walls 2' or wider get one
  • Box fill calculated; cables stapled within 8" of box and every 4-1/2'
  • Bored holes centered in stud, min 1-1/4" from face or nail-plated
  • AFCI protection on most living-area circuits; GFCI at kitchen, bath, laundry, garage, exterior, and within 6' of any sink
  • Panel: 30" wide x 36" deep clear working space, 6'-7" headroom, breaker handles max 6'-7" AFF
  • Smoke alarms in each bedroom, outside each sleeping area, each level; min 3' from supply registers and bath doors

Permits & inspection milestones

  • Electrical rough-in inspection
  • Service / meter release from utility

Field tips & tricks

  • Walk the lighting plan with the homeowner at rough, in the actual rooms, with switch boxes nailed. Changes cost $20 now, $2,000 later.
  • Set box depth for the finished wall thickness. Boxes recessed behind drywall are a code violation and a tedious fix.
  • Leave a labeled 12"-tail and a plan mark-up photo of every home run. Trim-out gets twice as fast.

Reference documents

View in library →

Field checklist

0 / 6 complete
  • Panel set and grounded
  • Boxes set to depth and height
  • Home runs pulled and labeled
  • AFCI / GFCI circuits mapped
  • Smoke / CO locations verified
  • Rough inspection passed
42–3 days

Low Voltage, Security & Pre-wire

Data, TV, audio, cameras, doorbell, and network head-end pre-wire.

Low Voltage

Prerequisites & handoff

  • Electrical rough substantially complete
  • AV / network plan

Critical measurements & tolerances

  • Keep low voltage min 12" parallel separation from line voltage; cross at 90° only
  • Cat6 max run 295' (100 m) including patch cords
  • TV outlets: box + conduit sleeve behind each display; 60"–66" AFF for wall-mounts
  • Network head-end: dedicated receptacle, ventilation, and a labeled panel

Permits & inspection milestones

  • Low-voltage permit where required; usually inspected with electrical rough

Field tips & tricks

  • Pull a spare conduit from head-end to attic and to the media wall. Future you will pay real money for it.
  • Label both ends of every cable with a printed tag before drywall. Toning 40 unlabeled drops is a lost day.

Reference documents

View in library →

Field checklist

0 / 5 complete
  • Data / coax pulled and labeled
  • Camera and doorbell runs in
  • Speaker wire and backboxes set
  • Head-end location powered
  • Spare conduits installed