Rough Inspections & Envelope

The pre-drywall gate. Nothing gets covered until every trade signs off.

Typical duration: 1–2 weeks
2 steps
0/11 complete
12–4 days

Pre-Drywall Multi-Trade Walk & Framing Inspection

Coordinated sign-off from framing, plumbing, mechanical, electrical, and the building official.

Builder / Super
Inspections
Framing

Prerequisites & handoff

  • All rough-ins complete and tested
  • Fire blocking and draft stopping installed

Critical measurements & tolerances

  • Fire blocking at all concealed vertical/horizontal intersections and max 10' in stud cavities
  • Draft stopping in floor / attic assemblies over 1,000 sq ft where required
  • Penetrations through top and bottom plates sealed
  • Notch / bore repairs plated and verified

Permits & inspection milestones

  • Framing inspection
  • Combined rough or 4-way inspection where offered
  • Engineer letter for any field-modified structure

Field tips & tricks

  • Do your own punch walk with a flashlight the day before the inspector. You will find 20 items; they only need one to fail you.
  • Photograph every wall bay before insulation. The best as-built documentation you will ever have costs 30 minutes.
  • Invite the homeowner to a pre-drywall walk — it is the last easy chance for changes and it builds enormous trust.

Reference documents

View in library →

Field checklist

0 / 5 complete
  • Fire blocking / draft stopping complete
  • All trade rough inspections passed
  • Framing inspection passed
  • Wall bays photographed
  • Homeowner pre-drywall walk done
23–6 days

Air Sealing, Insulation & Blower-Door Prep

Seal the envelope, then insulate to the energy code and verify by test.

Insulation

Prerequisites & handoff

  • All rough inspections passed
  • Windows and doors installed

Critical measurements & tolerances

  • Typical code targets: R-13 to R-21 walls, R-38 to R-60 ceilings, per climate zone
  • Blower-door target commonly ≤ 3.0 ACH50 (climate zones 3–8) or ≤ 5.0 ACH50 (zones 1–2)
  • Insulation installed to Grade I: full contact, split around wiring, no compression or voids
  • Baffles maintain min 1" clear vent space at eaves; attic vent net free area 1:150 (or 1:300 with balanced vents)
  • Fire caulk rated penetrations; foam-seal all top plate, rim joist, and can-light penetrations

Permits & inspection milestones

  • Insulation inspection before drywall
  • Blower-door test and energy compliance report

Field tips & tricks

  • Air seal before insulation, not after. Insulation without air sealing is a filter, not a barrier.
  • Split batts around wiring and plumbing instead of squashing them — compression is the most common Grade I failure.
  • Run a pre-test blower door before drywall so leaks are still reachable. Fixing 5 ACH after paint is misery.

Field checklist

0 / 6 complete
  • Top plates and rim joists sealed
  • Penetrations fire-caulked
  • Baffles installed
  • Insulation to spec, Grade I
  • Pre-drywall blower door run
  • Insulation inspection passed